- Cause
- You used the Project Configuration to define new sprints, but did not actually create new sprints in the Backlog
- Resolution
- From Backlogs>Planning Create new sprints
- It will use the predefined sprints from the project configuration if they were defined
- Otherwise, you can define new sprints
- These will now display in the delivery plan